Have made the final changes to the fiberglass Prop shaft tubes , have added a bit more beef to the end with the cutlass bearing , better to be over strong than have a weakpoint .
The basic tube is 10mm thick fiberglass , but the end has additional material to bring it up to 16mm
Made an initial thin tube by rolling wetted out fiberglass cloth over a steel pipe , removed when set by slitting it off , had to be a tight fit as the cutlass bearing is supposed to be a tight fit . Rejoined the tube ( while ensuring straightness and sizing ) and added more layers of cloth to bring it up to the 10mm thickness . Finally added the extra cloth to the cutlass bearing end ( just last weekend ) .
Cutlass bearing is a tight press fit and its as straight as a dye , must remember process as i need to make another one as well ( darn catamaran ) .
Have fitted the tube into a piece of the Keel structure , this will then be laminated into the main Keel.
Tuesday, 1 December 2015
Tuesday, 17 November 2015
Thinking about a support Boat
Jigsaw will require a tender / support boat with it as most of the construction will take place when its already in the water .
First thought was
With a cross section of
A bow door like a landing craft and a fully enclosed floor for boyancy , problem is its not wide enough for all the jobs it needs to do , Maybe a catamaran version ?
First thought was
With a cross section of
A bow door like a landing craft and a fully enclosed floor for boyancy , problem is its not wide enough for all the jobs it needs to do , Maybe a catamaran version ?
Sunday, 1 November 2015
Time to Deliver my Second Baby
Bow section on the Second hull is now ready for its first look at a bright new world .
Have made some changes to the rollers that the boat will move on , so hopefully it won't be as big a squeeze as the first time we did this .
Slowely she makes her way , a naked baby this one as the garage is too full of wood to allow me to wash her down and paint , so outside we go !
The changes i made to the rollers were sucessful , we had at least an inch of clearance this time , created steel L brackets that were attached to the main bulkhead that allowed me to lower the assembly closer to the ground .
And then , just like a normal birth , she rushed out to see the sunshine , but OOP's
Things come to a sudden stop , the new low-riders are low alright , a little too - low for the uneven concrete surface , ah-well , we are outside now . Time for Baby's first bath .
A quick wash and a rub-down , time to paint this baby .
Just a light coat of Hempel's Light Primer , this will make it easier to spot any inperfections in the finish so we can correct these with a bit of sanding or filler .
As with the other hull , this outside surface has the partial skin cover that allows for the rest of the side to be added later but with plenty of surface attachment .
The rest of the paint hasn't turned up yet so the additional layers of primer will need to wait .
Sunday, 18 October 2015
Almost finished the Sharp bit !
It been a while since my last post , so quite alot has been done ,
The plywood party is complete so the dual layers of plywood have been fitted .
Have also added the conical bow section , the laminated forefoot capping strip , the external keel and the sides have also been fiberglassed .
Have left some of the peelply on the sides as it helps protect them while I fiberglass the bottom of this section .
Had a couple of mis-adventures with this section , created the conical bow section and fiberglassed the inside of the wooden strips used to create the shape , but when i went to refit to the bow the shape had changed slightly but since the glass had started to go hard was forced to cut the section in two and reglue / re-epoxy , two layers of 1200gm fiberglass just doesn't want to bend once it starts going off !.
The Laminated forefoot capping strip was made in-situ and is made from strips of 6mm solid timber , on the other hull I had used 8mm strips , but they were differcult to bend , thus 6mm for this section , but it wasn't without its issues , pays to remove the holding screws ( for laminating ) before the epoxy goes fully off , was a little late on a couple of them , the heads on the screws snapped off when attempting to remove ( 12g x 50 mm ) , so the shafts are still buried inside the lamination , lucky they were close enough to the middle of the section so they weren't exposed when i shaped the forefoot .
The plywood party is complete so the dual layers of plywood have been fitted .
Have also added the conical bow section , the laminated forefoot capping strip , the external keel and the sides have also been fiberglassed .
Had a couple of mis-adventures with this section , created the conical bow section and fiberglassed the inside of the wooden strips used to create the shape , but when i went to refit to the bow the shape had changed slightly but since the glass had started to go hard was forced to cut the section in two and reglue / re-epoxy , two layers of 1200gm fiberglass just doesn't want to bend once it starts going off !.
The Laminated forefoot capping strip was made in-situ and is made from strips of 6mm solid timber , on the other hull I had used 8mm strips , but they were differcult to bend , thus 6mm for this section , but it wasn't without its issues , pays to remove the holding screws ( for laminating ) before the epoxy goes fully off , was a little late on a couple of them , the heads on the screws snapped off when attempting to remove ( 12g x 50 mm ) , so the shafts are still buried inside the lamination , lucky they were close enough to the middle of the section so they weren't exposed when i shaped the forefoot .
This weekend I have been fiberglassing the bottom sections , one side of the bottom section was done yesterday and the other side today , the glass overlapps the keel and the chines ,giving two layers of cloth at these points .
So now all i need to do on this section is remove the peelply and prepare the section for painting ,
joy oh joy , more sanding !!!
Sunday, 16 August 2015
Frames Done , Time for a Plywood Party
These curvy bits may look great , but there is a lot of work getting them straight ( HUH ) , well correct anyway . Framing is complete , now I just need to fit the connecting bolts into the frame and we can start the Plywood Skinning of the first section of the second Hull . Each stringer ( longitudinal frame ) is bolted to the transverse frames , originally planned on using Stainless Steel bolts but changed to stainless coach screws , easier and as I soak each hole in activated epoxy resin the holding strength is much better than a standard fit , thanks to the WEST guys for that suggestion in their book .
Garage is a bit messy , but didn't have enough solid timber for this section so had to get another shipment so got enough wood for the next section as well . Have timber stacked everywhere . Plywood sheets ( 18 x 12mm and 4 x 18mm ) have also arrived , so are stacked on the side of the garage , have barely enough room to move , yet along work . At least this being the bow section , its at least narrow at the entrance anyway .
This being the starboard hull the first bulkhead 45 degree additional section is on the left of these pictures , would have been Embarrassing if I had made two Port hulls .
Thursday, 28 May 2015
The Jigsaw pieces lineup again
Have completed building the frames , now we start the assembly process , first to be done is the attachment of the stem frame to the Primary Bulkhead , relatively simple , couple of stainless coach bolts and an amount of Epoxy glue .
These are the sheet frames , these will run from the Primary bulkhead , rearward at 900mm intervals .
Additional gussets are yet to be fitted to the non-sheet side of the solid timber sections , do these as i fit the longitudinal stringers .
These are the sheet frames , these will run from the Primary bulkhead , rearward at 900mm intervals .
Additional gussets are yet to be fitted to the non-sheet side of the solid timber sections , do these as i fit the longitudinal stringers .
Sunday, 3 May 2015
Bad case of Deja Vu
Section 4 is now outside awaiting its final Keel installation with the associated power train components , Manufactured my own Propeller shaft tube out of Fiberglass resin and 1200 gm quad-axial cloth . Came out quite well ( pictures later ) .
I have also started on the starboard hull Stem core .
This this the base structure for the stem and is made mostly from 40 x 150 kauri , additional lamination's of solid timber are added to the sides of this structure to build up to what is required . Its also reinforced by a plywood center-line frame , in the port hull we made this from 18mm ply , but I was not happy in the way this was connected to the stem core so in this hull I have changed to a box type frame made from 9mm sheet ply and solid timber , the ply will go both sides of the timber structure and attaches easily to the stem core ( only one side affixed in this picture ) as the core and the frame are the same width .
The last time I built one of these was 28 months ago , who's idea was it to build a bloody catamaran ,
Talk about Deja Vu !!
I have also started on the starboard hull Stem core .
This this the base structure for the stem and is made mostly from 40 x 150 kauri , additional lamination's of solid timber are added to the sides of this structure to build up to what is required . Its also reinforced by a plywood center-line frame , in the port hull we made this from 18mm ply , but I was not happy in the way this was connected to the stem core so in this hull I have changed to a box type frame made from 9mm sheet ply and solid timber , the ply will go both sides of the timber structure and attaches easily to the stem core ( only one side affixed in this picture ) as the core and the frame are the same width .
The last time I built one of these was 28 months ago , who's idea was it to build a bloody catamaran ,
Talk about Deja Vu !!