Rotation cradle is still under the bow section ( 5 ) so need to create a temp cradle to hold it to release the main cradle for its duty , will do this soon as section 7 is almost ready to come out of the shed and need to create space for it .
The last couple of weeks we have been skinning section 7 in the 2 layers of 1/2 inch plywood.
This is now complete -
Last weekend we started on the fiber-glassing of this section
Do the sides first , as they are the easiest , the bottom layer overlaps this layer at the chine .
Glass is installed using the " Wet Method" , activated resin is painted on the plywood , rolled for 10-15 minutes as the plywood de-gasses trapped air and then we add more resin in preparation for the class cloth , roll the glass on and smooth out , then add more resin to "wet out" the cloth .
Once this is sticky and stable , we then add another layer of resin and attach the Peel-Ply and smooth out as much as possible .