Thursday, 4 April 2019

External Keel Laminations

Got bored working on the house ( or restless ) , so looked at completing some outstanding issues with the stern sections , The External keel on section 4 / 8 still needed to be done as well as the rudder stub and rudder bearing strut .
First item was the lamination's of solid timber to form the External keel , this was made out of multiple pieces of 100 x 50 kauri  , cut to shape and laminated into position .






 , built another stern tube as with previous stern section and added into lamination as required .





The keel line runs straight from mid-ship rearward , the tunnel in the rear section of the hull means less draft and better protection for the propeller .

The capping strip is slightly wider than the lamination's  so used epoxy filler to create a flat surface on the sides , then covered with multiple layers of unidirectional cloth to create a structual component to take the vibration from the prop and possible grounding capability .

Once the external keel was complete then proceeded on the rudder bearing strut and the rudder stub , the stub is required due to the turning limitations of having a rudder inside a prop tunnel .

In this picture you can see the tube for the bearings and the rudder stub , the stub is cut from the blanks for the rudder already created , glued into position around the tube and filled with expanding foam . Additional glass was then added to form the top of the stub .







After a coat of primer we then fitted  the rotating cradle around this section and rotated into the correct orientation .
This way up looks so much better .

In this picture you can see the finished external Keel , sterntube , tunnel and rudder stub , now just have to repeat this on the other hull , ( damn Catamaran )



Friday, 10 August 2018

A PAUSE IN THE PROCEEDINGS


Haven't posted in a while  , Sections 7 and 8 have been mostly completed by Mid 2017  ,  all sections now surround our house like a fence  . Google earth picture shows most of them and I have added the positions of the last 2 .






The bow of  Hull 2 almost extends over the back fence to the neighbors place .



This has given my Garage back so I was also able to start in on the rudder blades and rudder bearing housing .

Created a half form for the shape of the Rudder



And from this created a number of  fiberglass blanks





These will form the base of the Rudder Blades . Mounted these in a vertical jig and added  multiple layers of  resin impregnated Quad Axial cloth to build up to the desired thickness .
Since it was winter , had to pre-heat the resin so it was runny enough to saturate the cloth as Quad axial cloth is woven very tightly . Very messy job .






The final blade will require some filler on the outside to create a nice finish but by laminating
over a male mold the cloth wraps around the front in a continuous piece so structurally is much stronger .  The Design of the blade is a   MacLear Thistle  which allows for a greater rudder angle and acts like a side thruster at full angle .

Also created the rudder bearing tubes  , these were created like the stern tubes for the prop shafts , only a larger dia and much stronger due to the rudder shafts to be made from 2" Stainless Steel .








These have an internal Dia of 3" and a glass thickness of 5/8" and a length of 30" . The lower bearing will be Vesconite  , a  self lubricating thermoplastic and the upper bearing will be cast bronze .






The Rudder blade pieces ended up with a 3/8 " thickness , 36" tall  , 3 3/4 " width and length of 27"

These will still need to be trimmed to size  , a 4" section needs to be removed and glassed into the propeller tunnel as a base  , the rudder blade swings below this base .





I managed to get an old 2" prop shaft cheaply so will cut this into 2 lengths , add some tangs to it and use it as the rudder shafts . These will be glued into place and the rudders filled with high density foam .


Havn't gotten much done over the last year  , its transition time and this is going to be tricky , next phase of the construction will need to be done in a large shed  and the only way to fund this and the rest of the construction  is to sell the family house , Am currently renovating the house and organising family , not an easy task . Hopefully by the end of the year we will move the sections to the new location and continue the build .






Sunday, 6 November 2016

More Wet Sticky Stuff

Have fitted the external keel and prepared the bottom of this hull section for more of the Wet Sticky Stuff , the fiberglass on the sides has been faired into the bottom ply with more filler and more sanding followed by more sanding ( Oh Yeah ) .

Some of the peelply has been left on the sides for additional protection , but since the bottom layer of glass overlaps the keel  , some has been removed .


The bottom layer of glass runs from just above the chine  , across the bottom , over the keel and stops just over the other side of the keel , giving 2 layers at the chine and the Keel .
Problem with this wet sticky stuff is old men leaning over the hull wearing short shirts and exposing their hairy  bulging stomach's to such a messy substance , very messy indeed . Who needs to wax when there's fiberglass around !! .

Friday, 28 October 2016

The Boring Bits in the Middle !

Sections 6 and 7 are the most boring  , very little shape change  , so not very interesting , Same basic Construction though .  Section 6 was built off the bow section and when the shape was stable the bow section was removed and rotated ( earlier posts ) . When section 6 was complete it was used as the basis for Section 7 , when 7 was stable section 6 was removed and now sits awaiting its turn to be rotated .

Rotation cradle is still under the bow section ( 5 ) so need to create a temp cradle to hold it to release the main cradle for its duty  , will do this soon as section 7 is almost ready to come out of the shed and need to create space for it .

The last couple of weeks we have been skinning section 7 in the 2 layers of 1/2 inch plywood.

This is now complete -

 


 
Last weekend we started on the fiber-glassing  of this section
 

Do the sides first  , as they are the easiest , the bottom layer overlaps this layer at the chine .
Glass is installed using the " Wet Method" , activated resin is painted on the plywood  , rolled for 10-15 minutes as the plywood de-gasses trapped air and then we add more resin in preparation for the class cloth , roll the glass on and smooth out , then add more resin to "wet out" the cloth .
Once this is sticky and stable  , we then add another layer of resin and attach the Peel-Ply and smooth out as much as possible .



 

Saturday, 7 May 2016

Roll Me Over , Again !!

Section 6 is complete , so need to remove it from the shed as a new shipment of timber is due to arrive  for the next piece of the puzzle  . The bow section has been sitting in the front yard  , after its disconnection from section 6  , so its now time to Upturn it into something more akin to a boat . The cradle was round the back yard under one of the earlier sections so dragged it out and round the front yard and positioned it over Section 5 .

 
 

The Cradle is used for all sections of the main hulls so need to brace the hull inside the cradle , don't really want it moving during the rotation . Also need to bolt-on the semi-circular addons that allow for a smooth rotation .
 
 
 
Now we attach the ropes , chains and other bits and start the rotation ( time to panic ! )
 
 
 
Over we go  , nice and slow , try not to screw it up !
 
 
 
Making progress , ropes pulling from one way to make it roll , ropes in the other direction to stop it rolling by its own will ( don't ask , drama when we rolled section 2 still gives me nightmares)
 
 
 
 
This is when it has a mind of its own and all we can do now is to control the descent  , no more pulling  required , its on its way down .
 
 
 
Maximum load on descent chain at this time but its getting closer to its destination , taking it really  slow .
 
 
 
 
Phew !!! , its down  , I can Breathe again !! , Finally , something that actually looks like a boat .
 
Tomorrow I'll move this section into the side yard and we will look at getting section 6 out of the garage , I'll just remove the addons and manoeuvre this piece out of the way ( don't want to upset the neighbours as its taking up the shared driveway at the moment ) .








Tuesday, 1 December 2015

Stern tube ,is this where we launch torpedo's ?

Have made the final changes to the fiberglass Prop shaft tubes , have added a bit more beef to the end with the cutlass bearing  , better to be over strong than have a weakpoint .


The basic tube is 10mm thick fiberglass , but the end  has additional material to bring it up to 16mm


Made an initial thin tube by rolling wetted out fiberglass cloth over a steel pipe  , removed when set by slitting it off  , had to be a tight fit as the cutlass bearing is supposed to be a tight fit . Rejoined the tube ( while ensuring straightness and sizing )  and added more layers of cloth to bring it up to the 10mm thickness . Finally added the extra cloth to the cutlass bearing end ( just last weekend ) .
Cutlass bearing is a tight press fit and its as straight as a dye , must remember process as i need to make another one as well ( darn catamaran ) .

Have fitted the tube into a piece of the Keel structure , this will then be laminated into the main Keel.

Tuesday, 17 November 2015

Thinking about a support Boat

Jigsaw will require a tender / support boat with it as most of the construction will take place when its already in the water  .
First thought was

With a cross section of
A bow door like a landing craft and a fully enclosed floor for boyancy , problem is its not wide enough for all the jobs it needs to do  , Maybe a catamaran version ?

Sunday, 1 November 2015

Time to Deliver my Second Baby

Bow section on the Second hull is now ready for its first look at a bright new world .

 

Have made some changes to the rollers that the boat will move on  , so hopefully it won't be as big a squeeze as the first time we did this .
 
 
Slowely she makes her way  , a naked baby this one as the garage is too full of wood to allow me to wash her down and paint  , so outside we go !
 
 
 
The changes i made to the rollers were sucessful , we had at least an inch of clearance this time , created steel L brackets that were attached to the main bulkhead that allowed me to lower the assembly closer to the ground .
 
 







 
 
And then  , just like a normal birth  , she rushed out to see the sunshine  , but OOP's
 
 
 
Things come to a sudden stop , the new low-riders are low alright , a little too - low for the uneven concrete surface , ah-well  , we are outside now  . Time for Baby's first bath .
 
 
 
A quick wash and a rub-down  , time to paint this baby .
 
 
Just a light coat of Hempel's Light Primer , this will make it easier to spot any inperfections in the finish so we can correct these with a bit of sanding or filler  .
 

As with the other hull  , this outside surface has the partial skin cover that allows for the rest of the side to be added later but with plenty of surface attachment .
 
The rest of the paint hasn't turned up yet so the additional layers of primer will need to wait .




Sunday, 18 October 2015

Almost finished the Sharp bit !

It been a while since my last post , so quite alot has been done ,
The plywood party is complete so the dual layers of plywood have been fitted .


Have also added the conical bow section , the laminated forefoot capping strip , the external keel and the sides have also been fiberglassed .

 
Have left some of the peelply on the sides as it helps protect them while I fiberglass the bottom of this section .
Had a couple of mis-adventures with this section , created the conical bow section and fiberglassed the inside of the wooden strips used to create the shape , but when i went to refit to the bow the shape had changed slightly but since the glass had started to go hard was forced to cut the section in two and reglue / re-epoxy , two layers of 1200gm  fiberglass just doesn't want to bend once it starts going off !.

The Laminated forefoot capping strip was made in-situ and is made from strips of 6mm solid timber , on the other hull I had used 8mm strips , but they were differcult to bend , thus 6mm for this section , but it wasn't without its issues  , pays to remove the holding screws ( for laminating ) before the epoxy goes fully off  , was a little late on a couple of them  , the heads on the screws snapped off when attempting to remove ( 12g x 50 mm ) , so the shafts are still buried inside the lamination , lucky they were close enough to the middle of the section so they weren't exposed when i shaped the forefoot .

 
This weekend I have been fiberglassing the bottom sections  , one side of the bottom section was done yesterday and the other side today , the glass overlapps the keel and the chines ,giving two layers of cloth at these points .
So now all i need to do on this section is remove the peelply and prepare the section for painting  ,
joy oh joy  , more sanding !!!
 



Sunday, 16 August 2015

Frames Done , Time for a Plywood Party



These curvy bits may look great , but there is a lot of work getting them straight ( HUH ) , well correct anyway .  Framing is complete  , now I just need to  fit the connecting bolts into the frame and we can start the Plywood Skinning of the first section of the second Hull . Each stringer ( longitudinal  frame )  is bolted to the transverse frames  , originally planned on using Stainless Steel bolts but changed to stainless coach screws , easier and as I soak each hole in activated epoxy resin the holding strength is much better than a standard fit , thanks to the WEST guys for that suggestion in their book .



Garage is a bit messy  , but didn't have enough solid timber for this section so had to get another shipment so got enough wood for the next section as well . Have timber stacked everywhere . Plywood sheets ( 18 x 12mm and 4 x 18mm ) have also arrived , so are stacked on the side of the garage , have barely enough room to move , yet along work . At least this being the bow section  , its at least narrow at the entrance anyway .


This being the starboard hull the first bulkhead 45 degree additional section is on the left of these pictures  , would have been Embarrassing if I had made two Port hulls .

Thursday, 28 May 2015

The Jigsaw pieces lineup again

Have completed building the frames , now we start the assembly process , first to be done is the attachment of the stem frame to the Primary Bulkhead , relatively simple , couple of stainless coach bolts and an amount of Epoxy glue .

These are the sheet frames , these will run from the Primary bulkhead , rearward at 900mm intervals .
Additional gussets are yet to be fitted to the non-sheet side of the solid timber sections , do these as i fit the longitudinal stringers .

Sunday, 3 May 2015

Bad case of Deja Vu

Section 4 is now outside awaiting its final Keel installation with the associated power train components , Manufactured my own Propeller shaft tube out of Fiberglass resin and 1200 gm quad-axial cloth . Came out quite well ( pictures later ) .

I have also started on the starboard hull Stem core .

This this the base structure for the stem and is made mostly from 40 x 150 kauri , additional lamination's of solid timber are added to the sides of this structure to build up to what is required . Its also reinforced by a plywood center-line  frame  , in the port hull we made this from  18mm ply , but I was not happy in the way this was connected to the stem core so in this hull I have changed to a box type frame made from 9mm sheet ply and solid timber  , the ply will go both sides of the timber structure and attaches easily to the stem core ( only one side affixed in this picture ) as the core and the frame are the same width .


The last time I built one of these was 28 months ago  , who's idea was it to build a bloody catamaran ,
 Talk about Deja Vu !!